View Options
Show cost of a project based on the footprint construction cost.When
false, the total construction cost will be displayed instead.Show cost of a project rebased using time and location indexes.Indexes are displayed during benchmark reports.
Show cost of a project per functional unit.Example: A project cost of £10,000,000 of a block of 50 flats will display as
£200,000.Note: Displaying using the total construction cost or footprint cost will depend on other settings.